Project Title |
Construction of Six Lane access controlled Highway from Junction with Sector-62/65 dividing road on Faridabad –Ballabhgarh Bypass to Junction near KMP Expressway with NH-148N (Delhi-Vadodara Expressway) Section of NH-148NA (Design Ch. 33+000 to 59+063) in state of Haryana on Hybrid Annuity Mode under Bharatmala Pariyojana. |
Employer |
National Highways Authority of India, Plot No.G-5 & G- 6, Sector – 10, Dwarka, New Delhi – 110 075. |
Concessionaire |
DineshChandra Giriraj Infra Private Limited |
Independent Engineer |
Intercontinental Consultants and Technocrats Pvt. Ltd. |
Total Project Length |
26.063 Km |
Contract value |
Rs. 898.00 crores |
Letter of Award Date |
7th August 2020 |
Concession agreement signed |
21st October 2020 |
Appointed Date |
14 May 2021 |
Date of completion |
730 days from Appointed date (14/05/2023) |